Introduction:
An industry-leading technical services company recently relocated to a new facility at a prominent UK studio complex. With a vast inventory of heavy specialist equipment, the client required a significant increase in storage capacity to support its operations.
Project Overview:
Working alongside a global real estate consultancy, the client identified a mezzanine floor installation as the most effective solution. This flexible infrastructure allows for future adaptability and supports evolving operational needs.
Mezzanine Floor Details:
A mezzanine floor—an intermediate level between main floors—was chosen for its ability to maximize vertical space without altering the building’s footprint. Its relocatable nature also supports long-term flexibility and lease compliance.
Project Award:
Following a competitive tender process, Avanta UK Ltd was selected to deliver the project. With a tight lead time and complex requirements, Avanta’s experience in turnkey storage solutions made them the ideal partner..
Avanta's Turnkey Solution:
- Mezzanine Floor:
A 2,000 square meter fire-rated mezzanine, standing 5.2m to finished floor level and 4.7m clear underneath—ideal for pallet racking and large equipment storage. - Access:
Three staircases for personnel and a vertical goods lift plus pallet gate for load access. - Fire Rating:
One-hour fire rating achieved through fascia, column casings, a suspended ceiling, and two fire lobbies.
- Lighting & Electrical Installation:
A premium electrical system featuring Thorlux intelligent lighting, high-efficiency LED fittings with daylight harvesting and presence detection, and emergency lighting compliant with CIBSE standards. Power distribution was tailored to the facility’s operational needs.
- Floor Protection:
Heavy-duty 2.5mm industrial vinyl specified by the real estate consultancy to protect the mezzanine deck. - Pallet Racking:
Avanta designed, supplied, and installed British-manufactured adjustable pallet racking to match existing systems, with configurations up to 4m high.
- Additional Works:
Included Armco barrier and column protection, and relocation of existing racking.
Project Management:
Avanta UK acted as Principal Contractor for the 12-week project, managing all Health & Safety responsibilities and maintaining a constant site management presence to ensure smooth delivery.
The Latest Mezzanine Floor Production From Avanta UK
Related Projects
- 2000 m² Additional Floor Space Created For a UK Leading Specialist
- 350m2 Fire Rated Mezzanine Floor Installed For Sika Everbuild in Leeds
- Avanta Two by Two Tier Fire Rated Mezzanine Floor Project
- Elland’s Exertis Advent Rise To The Challenge With Multi-tier Mezzanine
- END to End Storage With Large Multi-Tier Shelving Solution
- Fire Rated Two Tier Mezzanine Floor for Elida Tigi
- Major Multi-tier Mezzanine Floor Project Completed by Avanta UK
- Multi-level Storage Solution for Fastest Growing Workwear Retailer
- Multi-Mezzanine Project for European Leading Provider of Consumer Packaging
- Multi-tier Mezzanine Floor & Shelving Project For GROUPAUTO
- Turnkey Multi-tier Mezzanine Floor Project for Multi-channel Fashion Retailer
- Zyro Fisher Mezzanine Floor Project
- 3PLUK Expand Capacity and Customer Base with the help of an Avanta Pick Tower